Town Engineer

Town Engineer

Office Hours

Monday - Friday

8:30 AM - 4:30 PM

Telephone: 603-447-3811, Ext. 232

  • James Badera, Town Engineer

James Badera

  • Jacqueline White - Project Administrator

CONWAY 40638 – MAIN STREET – EASTERN PROJECT TOWN OF CONWAY - LOCAL PUBLIC AGENCY (LPA) PROJECT #: 40638 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION Federal Aid Project: X-A004 (446) N.H. DOT Project No. 40638

Project Location: Town of Conway – Intersections of NH Route 16/ NH Route 153 (Washington and Pleasant Streets) and NH Route 16/ NH Route 113 in front of the Town of Conway Library property. Project Description: Intersection Improvements to NH Route 16 including the intersections of NH Route 16/ NH Route 153 and NH Route 16/ NH Route 113, as well as reconstruction, realigning, and widening respective roadways and approaches.

To view Project Plans: Click Here

To view Select Board Meeting Presentation on April 28, 2026: Click here

All project related, questions, comments, or complaints shall be emailed directly to the Town of Conway at: MainSt@conwaynh.org

***IMPORTANT NOTICE – June 17, 2026** EVERSOURCE AERIAL UTILITY WORK – PLEASANT ST. June 17, 2026 - (4) Eversource crews & (1) J. Roberts contractor crew will be doing the pre-planned scheduled outage on this day, with all customers previously being notified. June 18, 2026 - (1) Eversource crew will complete any clean up along with the last underground service work needed from existing pole # 2/4  (Note : This day should complete all necessary work in accordance with this work order.)


Project Update as of June 10, 2026

  1. Spectrum is the working on the transfer of their aerial facilities throughout the project area. They will notify the Town of any upcoming outages well in advance of performing work.
  2. Consolidated Communications is moving their aerial lines off of the existing poles in front of the Eastern Slope Dental property. This will allow the existing Eversource poles to be removed so that proposed drainage pipes can be installed. Consolidated is also in process of developing a plan for relocating their underground facilities in front of Conway Marketplace.
  3. AJ Coleman & Son, Inc. is completing the cap blocks at the top of the retaining wall in front the “Garg Complex” building, located at 15 Washington Street.
  4. AJ Coleman & Son, Inc. has started Phase #1 Drainage work along the East Side of Route 16 in front of the Eastern Slope Dental property. Work commenced at the existing pipe outfall location at the north of the property, and work will continue south towards the Irving Station in the next couple of weeks.



PROJECT OVERVIEW

The Main Street Project involves reconfiguring the NH Route 16 and NH Route 113 intersection, as well as reconstruction, realigning, and widening respective roadways and approaches.

The scope of work includes signalization improvements at both intersections, retaining wall construction, and stormwater drainage improvements.

The Preliminary Design phase for the project was authorized by NHDOT in 2018. The Notice to Proceed to the Construction Phase was received from NHDOT April 3, 2026.

The Town of Conway issued the Notice of Award of the construction contract to Alvin J. Coleman & Son, Inc. on April 7, 2026, with a construction start date of April 20, 2026. The construction will last 2 seasons, and will be completed by October 1, 2027.

2026 CONSTRUCTION SEASON (View Select board Meeting Link above)

The next 2-3 months will involve the construction of Phase 1. The 2026 Construction season will include Phase 1, Phase 2, and a portion of Phase 4 work.

PROJECT MANAGEMENT

This project is a Federally Funded project through the New Hampshire Department of Transportation (NHDOT), as the funds recipient through the Federal Highway Administration (FHWA).

NHDOT has provided funding for this project and it is referred to as a Local Public Agency (LPA) project, which is managed by the Town of Conway. LPA projects allow municipalities to develop, improve , and enhance New Hampshire’s transportation network.

Town Engineer, Jim Badera, P.E. is the person in responsible charge of this LPA project for the Town of Conway.

All project related information will be available at the Town Engineer’s webpage, not at the NHDOT website.

All project related, questions, comments, or complaints shall be emailed directly to the Town of Conway at: MainSt@conwaynh.org.

Project updates will be provided on the Town Engineer’s webpage every two weeks. These updates will also be presented at regularly scheduled Selectboard meetings.

Major traffic Alerts will be posted on the Town Engineer’s webpage and on the Town of Conway Facebook page.

TRAFFIC MANAGEMENT PLAN

The Traffic Control Plan (TCP) for the project provides two-way traffic throughout the entire duration of the project. Certain areas of the project will be widened with temporary pavement to maintain the current flow of traffic.

The TCP does not re-route or divert existing traffic patterns onto adjacent streets in the vicinity of the project during construction.

Advanced warning devices including message boards and permanent signage will make motorists aware of the construction activities. Flaggers will be used to direct motorists through the project site.

(Back to Town Departments)

Made with by TownCloud © Copyright 2026. All rights reserved.